Testing and commissioning overview
Prior to welcoming passengers on board, the light rail system undergoes a rigorous testing and commissioning process. This important phase of the project ensures the light rail is fully functional and safe to carry passengers before services commence.
Testing will occur in two phases, starting with the northern section, before moving to full alignment testing in 2026.
The light rail system and stops will remain closed to the public during the testing and commissioning phase until the project becomes operational.
Phase 1: July – December 2025
What’s happening:
Phase 1 focuses on the northern section of the alignment between Broadbeach South station and Miami North station. This phase verifies critical systems including signalling, communications, and electrical infrastructure in the north, while preparing the southern section for the next phase.
Activities include:
- Installation of poles, cantilever arms, and overhead wires in the north
- Some pole installation in the southern section (preparation for Phase 2)
- Energisation of overhead wires via Traction Power Substations
- Infrastructure, system and signal testing
- Tram testing.
Phase 2: July 2026 – Mid-2026
What’s happening:
Phase 2 expands testing and commissioning across the full alignment between Broadbeach South station and Burleigh Heads station, in preparation for passenger services. This phase ensures the entire Stage 3 route is fully integrated, safe, and ready for public use. Driver training also happens during this phase and all systems are rigorously tested to confirm readiness for passenger services.
Activities include:
- Installation of remaining poles and wires in the southern zone
- Full signal and communications testing across the entire alignment
- Extensive driver training
- Tram testing and running to timetables
- Cutover to the Operational Control Centre
- Operational readiness testing for all systems, stops, and vehicles.
Stay informed
Follow us on social media for updates
Subscribe to our newsletter
Visit our interactive map for information on current works
Have a question? Check out our FAQs below
Get involved
Check out the Safety Tram page for information and resources for schools and the community about safety on and around light rail.
| Resource | Description | Link |
|---|---|---|
| Overhead wire and energisation factsheet | For information on overhead wire installation, energisation and safety tips view our factsheet | Safety Tram - Factsheet.pdf |
Frequently Asked Questions (FAQs)
Overhead wires are being installed to power the trams in the lead up to passenger services starting. This follows the installation of 137 overhead poles and marks a key step towards testing and commissioning.
Energisation is a key milestone in preparing the light rail system for testing and future operations. It involves powering the overhead wires to deliver 750 volts of electricity to the trams. This process also includes activating traction power stations and connecting the system to the Energex network. Once energised, the infrastructure can safely support tram movements and allow for comprehensive testing of electrical and operational systems.
It is important to treat all overhead wires as live. Once powered, they carry 750 volts, which is enough to cause fatal injury if touched. Please keep a safe distance at all times.
Yes, it is safe to travel near the wires but always use designated crossings and obey road rules. Whether you are on foot, riding a bike or driving, please follow signage and take extra care. Oversized loads may require a permit.
Testing will begin in November 2025 between Broadbeach South station and the future Miami North station.
Stage 3 testing is being delivered in two parts, with the northern section completed first. This allows us to begin testing earlier in the north while construction continues in the south. Full alignment testing will occur in 2026.
No, trams will be running as part of controlled testing only and are not available for passengers during this phase.
Testing will occur across day and night shifts. Weekday testing is planned between 8pm and 6am, while weekend testing may happen at any time.
Some noise and activity may be noticeable, particularly during night testing. We appreciate your patience as we complete this essential phase to ensure the safety and reliability of the new service.
Passenger services are expected to commence in mid-2026, following the successful completion of testing and commissioning across the full Stage 3 alignment.
Construction works are wrapping up in the north between Broadbeach and Miami but construction activities are scheduled in 2026 between Miami and Burleigh Heads. Sign up for updates to stay informed.
While some noise and activity may be noticeable during testing, every effort will be made to minimise disruption. Access to businesses and homes will be maintained, and safety signage will be in place. We encourage everyone to stay informed and take care around work zones.